Skip to content

Latest commit

 

History

54 Commits

Folders and files

Repository files navigation

cpp-critical-path-validator

license: MIT python: 3.10+ tests version: 0.3.1 AACE: 49R--06

Critical path validation, logic health assessment, and optimization recommendations for Primavera P6 schedules — plus a full DCMA 14-Point Assessment.

Maintained by Critical Path Partners — a forensic-scheduling consultancy.

Companion to cpp-cpm-engine and cpp-xer-parser.


Scope and status

This is v0.3.1, and it is a public subset. Critical Path Partners maintains a larger internal validator; what this repository publishes is the nine-check core, the DCMA 14-Point assessment, the driving-path tracer and the HTML dashboard. It does not carry every check or output the internal version has.

Nothing here is a stub. The code in scripts/ is the code that runs, the tests in tests/ are the tests that guard it, and CI runs them on three operating systems across Python 3.10 to 3.12. What this repository is not is a mirror of the internal tool, so a report produced by Critical Path Partners should not be assumed to have come from this file set.

scripts/xer_parser.py is vendored byte for byte from cpp-xer-parser at release v0.2.1 (commit ca39d88), and scripts/validation.py and scripts/config_profiles.py are that release's files too, so the validator stands alone with no install step. CI verifies the vendored xer_parser.py against that pinned commit on every push, and separately reports, without failing the build, when upstream has moved past it.


What it does

This validator answers the question every scheduler and every claims expert eventually asks: is this critical path actually correct, or is it artificial?

It runs nine independent checks on a Primavera P6 schedule:

# Check What it catches
1 Critical path identification Are CP activities reasonable in count and % of incomplete work?
2 Constraint-driven criticality Hard constraints overriding network logic — the #1 source of false CP.
3 Open ends Missing predecessor / successor on incomplete activities.
4 Relationship quality FF / SS on CP without an FS backbone (fragile CP).
5 Lag analysis Negative lags (leads) on CP that mask true duration.
6 Out-of-sequence progress In-progress activities ahead of their predecessors.
7 Near-critical fragility Activities with TF 1–10 days that could become the new CP with minor slip.
8 Logic continuity Activities that contribute work but have no logic path to project finish.
9 Constraint saturation Schedule-wide hard-constraint density vs DCMA 5% threshold.

Plus a CP Confidence Score (0–100, weighted across all 9 checks), an HTML dashboard, a DCMA 14-Point Assessment with all 14 checks, and a driving-path tracer.


Why this validator

The critical path is the single most consequential output of any schedule. Bid pricing depends on it. EOT entitlement turns on it. Forensic claims live or die on it.

And yet — in the field — far too many critical paths are artificial: forced by hard constraints, broken by open ends, made fragile by negative lags, or unconnected to the project finish milestone. A scheduler who relies on the CP without first auditing whether the CP is real is making a load-bearing decision on unverified ground.

The checks in this validator come out of court-filed forensic schedule analysis, so the audit is rigorous. Every finding is structured, cited (DCMA-EA PAM 200.1, AACE 49R-06), and includes the full list of affected activities, never truncated.


Install

git clone https://github.com/danafitkowski/cpp-critical-path-validator
cd cpp-critical-path-validator
# No external runtime dependencies. Just put scripts/ on your sys.path.

Pure Python 3.10+. The repo bundles its own copy of xer_parser.py plus minimal validation.py / config_profiles.py stubs, so it stands alone without separately installing companion repos.


Quick start

import sys
sys.path.insert(0, 'scripts')

from xer_parser import parse_xer
from cp_validator import validate_critical_path, generate_dashboard

# Parse the schedule
data = parse_xer('path/to/your.xer')

# Run all 9 checks
results = validate_critical_path(data)

# Generate the HTML dashboard
generate_dashboard(results, 'cp_validation_report.html')

# Or interrogate the results dict directly
print(f"CP Confidence Score: {results['overall_score']}/100")
print(f"CP Confidence Band:  {results['overall_confidence']} ({results['overall_rating']})")
print(f"DCMA-14 worst:       {results['dcma_worst_severity']}")

for check_name, check_data in results['checks'].items():
    print(f"  {check_name}: {check_data['rating']} — {check_data['note']}")

DCMA 14-Point Assessment

A separate, well-defined check suite with established federal-contract heritage.

from xer_parser import parse_xer
from dcma14 import dcma_14_assess

data = parse_xer('current.xer')
baseline = parse_xer('baseline.xer')  # optional; required for BEI

report = dcma_14_assess(
    data,
    baseline_data=baseline,
    profile='commercial',   # or 'nuclear' or 'mining'
)

print(f"DCMA Score: {report['dcma_score']} of {report['dcma_max']} assessed")
print(f"Not assessed: {report['dcma_not_assessed']}")
print(f"CPLI: {report['cpli']}")
print(f"BEI:  {report['bei']}")

for check_id, check in report['per_check'].items():
    print(f"  {check_id}: {check['severity']} — {check['message']}")

The check ids follow the numbering of DCMA-EA PAM 200.1, ending DCMA-11-MissedTasks, DCMA-12-CriticalPathTest, DCMA-13-CPLI and DCMA-14-BEI. The score is out of the criteria the file could support: one that cannot be evaluated (BEI with no baseline, the Critical Path Test where nothing structural decides it, the float-dependent criteria on a file with no computed float) is reported INFO, left out of both numbers and listed in dcma_not_assessed; it never scores.

Three profiles bundle out of the box:

Profile Use case
commercial Generic commercial-construction defaults
nuclear Tightened thresholds for nuclear / heavy energy
mining Relaxed thresholds for resource-driven mining work

dcma_14_assess takes one of these names. It does not take a threshold dict: the bundled config_profiles.get_profile looks the profile up by name, and a dict raises TypeError. get_profile returns a copy of a profile's thresholds for reading:

from config_profiles import get_profile, list_profiles

print(list_profiles())    # the profile names dcma_14_assess takes
print(get_profile('nuclear')['dcma_high_duration_max_days'])
report = dcma_14_assess(data, profile='nuclear')

To grade against other thresholds, add a profile to _PROFILES in scripts/config_profiles.py, with every key the bundled profiles have, and pass its name.


Blank activity calendars

A schedule converted from MS Project (by MPXJ, for example) leaves TASK.clndr_id blank for every task without a task-level calendar. A blank id means the project calendar, and the validator reads it that way: before any check runs, each activity takes its own calendar, else the project's (PROJECT.clndr_id), else the calendar flagged default_flag = 'Y'. The parsed data is not modified.

results['calendar_resolution'] says what happened, and results['dcma_14']['calendar_resolution'] says the same for the activities DCMA-14 assessed. It gives the count of blank ids resolved, the calendar they were resolved onto, and every activity left with no usable calendar. An activity is left without one when its id is blank and the file names no project or default calendar, or when it names a calendar the file does not declare. Such activities draw a High "Activity Calendar" recommendation and a dashboard section that lists them, because their float and duration can only be read at a flat 8 h/day.


Driving path tracer

from dcma14 import trace_driving_path

# Walk back from an activity through its driving predecessors
chain = trace_driving_path(data, task_code='A1050.20')
print(' -> '.join(chain))

trace_driving_path returns a list of activity codes: the earliest driver it reached first and the activity you named last, or an empty list when the file has no activity with that code. At each step it follows the relationship marked driving (driving or driving_path_flag set to Y on the TASKPRED row) and, where none is, the predecessor that finishes latest, whatever the relationship type or lag. It stops after the first predecessor that is complete or finishes before the data date; where it finds no predecessor to follow (none left, none with a finish date, or one already in the chain); and after 200 predecessors, so a longer chain comes back without its earliest part. It returns codes only, with no float or relationship type.


Constraint taxonomy

Critical-path-validator distinguishes four tiers of constraint behavior:

Tier Codes Behavior
HARD_ABSOLUTE CS_MANDSTART, CS_MANDFIN P6 enforces the date regardless of network logic.
HARD_DATE CS_MSO, CS_MEO Pins the activity to a specific date; predecessor slips don't move it.
SOFT CS_MSOA, CS_MSOB, CS_MEOA, CS_MEOB Bounds the activity in one direction; logic drives the other edge.
PREFERENCE CS_ALAP Changes scheduling preference (late-date scheduling); no date bound.

Recommendations are tier-specific so schedulers know whether they are removing a Mandatory (overrides logic) or a Start-On (pins a date).


CP Confidence Score

Weighted average across all 9 checks (weights sum to 1.00):

Check Weight
Critical path identification 5%
Constraint-driven criticality on CP 17%
Open ends on CP 20%
Relationship quality on CP 13%
Lag issues on CP 15%
Logic continuity 10%
Near-critical fragility 10%
Out-of-sequence 5%
Constraint saturation (schedule-wide) 5%

Score bands. validate_critical_path returns the score as results['overall_score'], rounded to one decimal, the band as results['overall_confidence'] and its colour as results['overall_rating']. The band is set on the unrounded score, so a score that rounds up to a band's lower edge stays in the band below it.

Score overall_confidence overall_rating Meaning
80 or more High Confidence GREEN CP is logic-driven and reliable.
60 to under 80 Moderate Confidence AMBER CP has issues but is directionally correct.
40 to under 60 Low Confidence AMBER CP needs significant corrections.
under 40 Unreliable RED CP is artificial; do not rely on it for planning.

Two rules sit on top of the bands:

  • A logic cycle. A schedule whose relationships loop back on themselves has no forward pass and no critical path, whatever its stored float says. The validator looks for cycles before any check runs. Where it finds one, results['cycle_detected'] is True, results['cycles_found'] lists the cycles found, each as a closed chain of activity codes (cycles_found_task_ids as task ids), the score is 0, the band Unreliable and the rating RED, and a Critical "Network Cycle" recommendation names a cycle to break. The nine checks still run, for triage.
  • A RED check caps the headline. The score is a weighted average, so one RED check can sit under a GREEN average. Where any check is RED, the rating cannot be GREEN (it reads AMBER) and High Confidence reads Moderate Confidence. The score is left as computed; results['overall_rating_capped_by_red'] is True and results['red_checks'] names the RED checks. The two bands below 60 are unchanged.

The score grades logic health from the nine checks, and the results say so: results['overall_rating_scope'] is 'logic_health' and results['overall_rating_label'] is 'Logic Health'. It is not a DCMA-14 verdict. The DCMA-14 report embedded in the results (results['dcma_14']) can say BLOCK while the score reads GREEN, for example for an actual start after the data date, so its worst severity is also given at the top level: results['dcma_worst_severity'] is BLOCK, WARN, INFO or PASS, or None where DCMA-14 did not run, and where it ran results['dcma_blocks_despite_logic_rating'] is True for a BLOCK. The dashboard shows it under the gauge. Neither changes the score.


AACE alignment

The validator cites:

Reference What it covers
AACE Recommended Practice 49R-06 Identifying the Critical Path (LPM / TFM / MFP)
DCMA 14-Point Assessment The 14 schedule-quality metrics (DCMA-EA PAM 200.1)
NDIA PASEG Baseline Execution Index

Earlier revisions of this table also listed AACE 24R-03 and AACE 67R-11 with descriptions that were wrong: 24R-03 is "Developing Activity Logic", has no numbered sections, and is not a criticality standard; 67R-11 is "Contract Risk Allocation", not a forensic-competency document. Nothing in this repo cites either, so both rows were removed. The DCMA row previously misattributed the 14 metrics to federal acquisition regulations; their actual home is DCMA-EA PAM 200.1.


Running the tests

python tests/test_cp_validator.py     # validator core
python tests/test_dcma14.py           # DCMA 14-Point
python tests/test_cp_forensic.py      # forensic-correctness regressions

Or with pytest:

pip install pytest
pytest tests/

All tests build their XER fixtures synthetically in memory; no real client XER files ship with the repo.


Integration with the CPP forensic suite

CP validation is the first thing Critical Path Partners runs on a new XER, checking whether the CP is real before any forensic delay analysis, time impact analysis, or claims-package work begins. That job is done by the internal validator described under Scope and status; this repository publishes its nine-check core so anyone can run the same checks, without the two outputs described below.

When cpp-cpm-engine is on the same sys.path (its python_reference/ folder), Check 3 uses the engine's working-day arithmetic to decide which activities finish with the network: a finish at one working day's close and one at the next working day's opening count as the same instant on the activity's calendar. Without the engine, Check 3 matches finishes by day only. checks.open_ends_cp.finish_match says which of the two Check 3 ran (working-day or same-day). CI runs against the engine commit recorded as CPM_ENGINE_PIN in .github/workflows/test.yml. Check 3's finish test is the only thing in the validator that uses the public engine.

Two outputs need code that neither this repository nor the public engine provides, so they do not run from a clone of this repository, with the public engine or without it:

  • Check 2's LPM cross-check, which compares the critical path the schedule reports with an independently computed longest path, needs a compute_lpm function in the engine's cpm module. The public engine's python_reference/cpm.py does not have one; its header says it was stripped. Check 2 still runs its constraint-driven analysis, checks.constraint_driven.lpm_confirmed_false_cp stays empty, and checks.constraint_driven.lpm_error gives the reason: with the public engine it begins "cannot import name 'compute_lpm' from 'cpm'", and without the engine it reads "No module named 'cpm'".
  • The driver-chain narrative needs a driver_chain_narrative module, which this repository does not ship. results['driver_chain_narrative'] is an error block instead (an error naming the missing module, with empty narratives and manifest), and the dashboard's Driver-Chain Narratives section shows that error where the narratives would be.

License

MIT — see LICENSE.

You may use this validator in commercial forensic consulting, in academic research, in your own scheduling product, in court-filed expert reports. Just keep the copyright notice.


Contributing

See CONTRIBUTING.md. Bug reports and pull requests are welcome.


Companion repositories


Strategic note

Critical Path Partners is a forensic-scheduling consultancy. We open-source the foundational tooling because every academic, every solo forensic, every contractor's internal scheduler now has a reason to install CPP and a citation pathway. The math is a commodity; the workflow and discipline are not.

If you ship something built on this validator, we'd like to hear about it: criticalpathpartners.ca.

About

Critical Path Partners - critical path validation, DCMA 14-Point assessment, and logic health review for Primavera P6 schedules

Topics

Resources

Contributing

Security policy

Stars

0 stars

Watchers

0 watching

Forks

Releases

Packages

Contributors

Languages